Highway 65 Rebuild: SB 65 Closed From Sunshine To Battlefield Starting Aug. 4th

Highway 65 Rebuild: SB 65 Closed From Sunshine To Battlefield Starting Aug. 4th

Highway 65 Rebuild: SB 65 Closed From Sunshine To Battlefield Starting Aug. 4th

A project to rebuild Highway 65 in Springfield is starting up again August 4th.

The first part of the final phase will close southbound Highway 65 from Sunshine to Battlefield.

A couple detours will be in place along I-44 and Highway 60.

MoDOT says to expect major traffic delays over the next couple months and is asking drivers to starting thinking now about how they plan to get around the construction.

MoDOT says Highway 65 carries about 70-thousand cars a day through Springfield.

Folks can sign up to get email updates on the project. Click here to register.

MORE INFORMATION FROM MODOT:

Wednesday-Friday, July 31-August 2

  • Nighttime lane closings on southbound Route 65

Sunday-Saturday, August 4-10

  •  All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
  •  Southbound on ramp from Sunshine Street to Route 65 CLOSED
  •   Southbound off ramp from Route 65 to Battlefield Road CLOSED
  •   Southbound Route 65 lanes will close at 12:01 a.m. on Sunday, August 4, and reopen

Saturday-Tuesday, August 10-20

  • All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
  • Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
  • Southbound on ramp from Battlefield Road to Route 65 CLOSED
  • Southbound Route 65-to-westbound Route 60 ramp CLOSED

All lanes of Route 65 open during the Labor Day holiday (Tuesday-Friday, August 20-September 6)

Friday-Saturday, September 6-14

  • All northbound lanes of Route 65 CLOSED between Route 60 and Battlefield Road
  • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
  • Westbound Route 60-to-northbound Route 65 ramp CLOSED
  • Northbound off ramp from Route 65 to Battlefield Road CLOSED

Saturday-Friday, September 14-20

  • All northbound lanes of Route 65 CLOSED between Battlefield Road and Sunshine Street
  • Northbound Route 65 OPEN between Route 60 and Battlefield Road, but reduced to one lane
  • Northbound on ramp from Battlefield Road to Route 65 CLOSED
  • Northbound off ramp from Route 65 to Sunshine Street CLOSED
  • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
  • Westbound Route 60-to-northbound Route 65 ramp CLOSED
  • Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J

September 20-November 1

  • Nighttime lane closings for shoulder construction/guardrail/striping

 Work Scheduled:  

  • Installing erosion control devices in areas
  • Cutting concrete pavement in southbound lanes of Route 65 between Sunshine Street and Battlefield Road
  • Installing detour signs along I-44, Route 125, Route 60 and Route 360
  • Deploying electronic message signs in various locations throughout Springfield metro area

Prime Contractor: Emery Sapp and Sons, Inc. of Columbia

Completion Date: November 2019 (However, contractor plans to complete project by late September.)

Total Project Cost: $8.1 million