Nightime Road Work To Begin Monday in Southwest Springfield

CREATED Dec. 1, 2012

  • Print

Information from edited news release . . .

Greene County

Construction:
Kansas Expressway (Route 13) at James River Freeway (Route 60) Diverging Diamond Interchange in Springfield: Nighttime lane closings at times.  Work hours: 8 p.m. to 6 a.m. Completion: Sept. 2013.


West Bypass (Route 160) Bridge Replacement at I-44 in Springfield:
TWO-WAY TRAFFIC: One lane open in each direction on West Bypass over I-44 with traffic shifted to west side of bridge. Other traffic impacts: No left turns for northbound West Bypass traffic going westbound on I-44.  Must use Kearney Street westbound to I-44 Northbound West Bypass right lane must turn right at Kearney Street. Completion: May 2013
 
Chestnut Expressway/Route 65 Diverging Diamond Interchange in Springfield: Lane closings possible at times on Chestnut Expressway Project nearing completion. 

To see other road projects across the Ozarks .